Granger Construction has collaborated with the Charlotte Public School District on numerous bond proposals and construction projects.

1999 Bond

  • Constructed a new single-story middle school with three gyms, four locker rooms, one cafeteria, one auditorium/cafeteria, music wing, complete kitchen, district computer center, special education classrooms, 5th-8th grade wings with computer labs, media center and offices. Work also included renovations and upgrades to six elementary schools and their sites.

2001 Bond

  • Constructed a new auditorium/fine arts center at the high school and a new pool at the middle school.

Granger Construction has collaborated with the Charlotte Public School District on numerous bond proposals and construction projects.

1999 Bond

  • Constructed a new single-story middle school with three gyms, four locker rooms, one cafeteria, one auditorium/cafeteria, music wing, complete kitchen, district computer center, special education classrooms, 5th-8th grade wings with computer labs, media center and offices. Work also included renovations and upgrades to six elementary schools and their sites.

2001 Bond

  • Constructed a new auditorium/fine arts center at the high school and a new pool at the middle school.


2010 Bond

Additions and renovations to five of the District’s buidings including:

  • Charlotte High School - Two new and two renovated science classrooms/labs; girls and boys locker room addition; weight room renovation; administrative office addition; art room renovation; new heating and ventilation system; improved lighting; updated classroom technologies; new energy efficient windows and doors and reconfigured building entries to ensure all visitors pass by the administrative offices.
  • Charlotte Middle School/Upper Elementary - New building controls for heating and ventilation systems and new security cameras.
  • Parkview Elementary - New building entrance and main office; new roof sections; reconfigured building entries; new security cameras and energy efficient windows and doors; improved lighting and classroom technologies; renovated restrooms and computerized temperature controls.
  • Washington Elementary - New building entrance and main office; improved parent pick-up/drop-off loop; reconfigured building entries; new energy efficient windows and doors, improved lighting and classroom technologies; renovated restrooms and computerized temperature controls.
  • Weymouth Child Development Center - Entrance canopy removal and reconstruction; new energy efficient windows, rooftop exhaust units and HVAC unit.

Education

Charlotte Public Schools

COST:
Project 1 – $33.3 million (Bond 1999)
Project 2 – $18.7 million (Bond 2001)
Project 3 – $18.5 million (Bond 2010)

SQUARE FOOTAGE:
Project 1 – 180,000
Project 2 – 370,700
Project 3 – 354,404

SERVICE:
Construction Management

COMPLETION:
Project 1 – August 2002
Project 2 – October 2004
Project 3 – November 2013

ARCHITECT:
Projects 1 and 2 – Fanning/Howey Assoc.
Project 3 – Hobbs+Black