In 1999, Granger provides Ferris State University with a brand new basketball arena. In addition, they returned in 2008 to renovate the ice arena side of the sports complex.

The renovation of the ice arena included complete removal and replacement of the slab and ice-making system within and below the slab, all mechanical and electrical building systems and locker room renovations.

In 1999, Granger provides Ferris State University with a brand new basketball arena. In addition, they returned in 2008 to renovate the ice arena side of the sports complex.

The renovation of the ice arena included complete removal and replacement of the slab and ice-making system within and below the slab, all mechanical and electrical building systems and locker room renovations.

The basketball area included:

  • Seating capacity of 2,000 people
  • Locker rooms
  • Training facilites
  • An indoor track
  • Press box

The new multi-functional lobby included:

  • Ticketing
  • Concessions
  • Public restrooms
  • Gift shops
  • Athletic displays

 

Education

FSU Ewigleben Ice Arena, Sports Complex and Convocation Center

COST:
$3.3 million – Ice Arena
$6.7 million – Basketball Arena

SQUARE FOOTAGE:
48,000 – Ice Arena
41,000 – Basketball Arena

SERVICE:
Construction Management

START:
April 2008 – Ice Arena
March 1998 – Basketball Arena

COMPLETION:
August 2008 – Ice Arena
July 1999 – Basketball Arena

ARCHITECT:
DTS Architects + TMP Assosciates