Granger was selected to perform the 2012 North Campus Infrastructure project which involved the renovation and reconstruction of the existing steam utility system within MSU’s historic North Campus. Based on the team’s exemplary work within an extremely aggressive schedule, MSU hired Granger to also perform the remaining 3 phases of the project. Work included removal and replacement of high pressure and low pressure steam piping, electrical and communication vaults and ductbank, cast-in-place and precast steam tunnels and vaults, sanitary sewer, storm sewer and watermain as well as the complete reconstruction of roadways and sidewalks.

Granger was selected to perform the 2012 North Campus Infrastructure project which involved the renovation and reconstruction of the existing steam utility system within MSU’s historic North Campus. Based on the team’s exemplary work within an extremely aggressive schedule, MSU hired Granger to also perform the remaining 3 phases of the project. Work included removal and replacement of high pressure and low pressure steam piping, electrical and communication vaults and ductbank, cast-in-place and precast steam tunnels and vaults, sanitary sewer, storm sewer and watermain as well as the complete reconstruction of roadways and sidewalks.

Phase 1 (2012):

  • Electric Ductbank: 2502 LF
  • Telecom Ductbank: 3634 LF
  • Steam: 2577 LF
  • Crawl Tunnel: 591 LF
  • Walk Tunnel: 1986 LF
  • Steam Vaults: 8
  • Water: 4257 LF
  • Chilled Water: 100 LF
  • Storm: 2385 LF
  • Sewer: 815 LF

Start: Jan. 2012
Completion: Aug. 2012                 

Phase 2 (2013):

  • Electric Ductbank: 1173 LF
  • Telecom Ductbank: 1000 LF
  • Steam: 1444 LF
  • Crawl Tunnel: 211 LF
  • Walk Tunnel: 1234 LF
  • Steam Vaults: 7
  • Water: 4069 LF
  • Chilled Water: 628 LF
  • Storm: 802 LF
  • Sewer: 975LF

Start: Dec. 2012
Completion: Oct. 2013                

Phase 3 (2014):

  • Electric Ductbank: 800 LF
  • Telecom Ductbank: 100 LF
  • Steam: 1500 LF
  • Crawl Tunnel: 730 LF
  • Walk Tunnel: 400 LF
  • Steam Vaults: 9
  • Water: 2000 LF
  • Chilled Water: 440 LF
  • Storm: 950 LF
  • Sewer: 300 LF

Start: Dec. 2013
Completion: Nov. 2014

Phase 4 (2015):

  • Electric Ductbank: 550 LF
  • Telecom Ductbank: 180 LF
  • Steam 550 LF
  • Crawl Tunnel: 350 LF
  • Walk Tunnel: 200 LF
  • Steam Vaults: 4
  • Water: 990 LF
  • Chilled Water: 628 LF
  • Storm: 850 LF
  • Sewer: 590LF

Start: Feb. 2015
Completion: Aug. 2015

Higher Education

MSU North Campus Infrastructure

COST:
Total – $44.9 million
Phase 1 – $15.9 million
Phase 2 – $11 million
Phase 3 – $10 million
Phase 4 – $8 million

SERVICE:
CM At-Risk (with limited self-perform concrete)

ARCHITECT:
FTC and H