• LEED Gold Certification goal.
  • Up Time Institute Tier 3 Certification goal
  • This project is the first phase of a multiple phase project. Phase 1 includes a 200,000 s.f. building and site improvements.
  • (2) 10,000 s.f. data halls will be built out to support 2MW of computing power and cooling.
  • Future phases will increase the computing power from 2MW to 4MW in each data hall.
  • Phase 1 of the Data Center project includes:
    • (6) 2.5MW Emergency Generators
    • (2) Primary Switchgear line ups
    • (8) 3750 KVA Substations
    • (4) 670 Ton Chillers
    • (4) 808 Ton Cooling Towers
    • (40) CRAH Units

COST:
$115.7 million

SQUARE FOOTAGE:
250,000

SERVICE:
Design-Build

START:
September 2016

COMPLETION:
July 2018

ARCHITECT:
Integrated Design Solutions/IBI Group Michigan