Granger Construction completed renovations in eight district facilities to address four primary themes: safe secure entries, upgrades to the building envelope, mechanical and electrical upgrades to address cost of ownership, and additions for student capacity.
Granger Construction completed renovations in eight district facilities to address four primary themes: safe secure entries, upgrades to the building envelope, mechanical and electrical upgrades to address cost of ownership, and additions for student capacity.
- Clear Lake Elementary – Four classroom additions and office entry addition including new roof, exterior doors and windows throughout; and new vertical unit ventilators.
- Lakeville Elementary – Major classroom space reconfiguration including new roof, exterior doors and windows throughout; and new vertical unit ventilators.
- Oxford Elementary – Five classroom additions, office entry addition and kitchen addition; including new roof, exterior doors and windows throughout; and new vertical unit ventilators.
- All 3 Elementary above were phased renovation safely constructed throughout the school year in occupied K-6 buildings.
- Oxford Middle School – New natural turf athletic field and running track including new toilet and press box building.
- Oxford High School – New pre-engineering lab renovation, new track and synthetic football field and new tennis courts.
- Early Child Care – Provided renovated space at the existing district offices for a new centralized Early Child Care Center.
K-12
Oxford Community Schools
COST:
$25 million
SQUARE FOOTAGE:
859,000 (17,000 sq. ft. additions; 842,000 sq. ft. renovations)
SERVICE:
CM At-Risk
START:
May 2010
COMPLETION:
September 2012
ARCHITECT:
Integrated Design Solutions